HS2 Warwickshire Bridges: Community, Rail Infrastructure & Progress
The new Fosse Way bridge, part of the HS2 project, opens near Leamington, enhancing connectivity. This **railway** infrastructure project, delivered by Galldris, progresses in Warwickshire.

“`html
Introduction
The Fosse Way bridge, a 78m long structure, has opened near Offchurch, outside Leamington, as part of the HS2 project. The bridge, along with the nearby Offchurch Greenway bridge, was delivered by Galldris on behalf of Balfour Beatty VINCI, HS2’s main works contractor.
Fosse Way Bridge
The Fosse Way bridge carries the B4455 across the railway near Offchurch, outside Leamington. It is situated on the route of a Roman road between Exeter and Lincoln and is currently used by local traffic between villages around Leamington and Coventry. The bridge is 78m long and 14m wide, including space for a pavement.
Offchurch Greenway Bridge
The Offchurch Greenway bridge, which carries a walking and cycle path between Leamington and Rugby, opened shortly before the Fosse Way bridge. The Greenway follows the route of an abandoned railway line. This bridge is 68m long and 22m wide and will feature grass verges to facilitate wildlife crossings.
HS2 Project Progress
With the new bridges open, HS2’s contractors can begin demolishing the old road section to allow for the cutting that will accommodate the new railway. The Greenway currently crosses the B4455 at ground level. This crossing is scheduled to be replaced next year with a new bridge.
Statements from Project Leaders
Vicki Lee, HS2 Ltd’s Senior Project Manager, noted the importance of both bridges in maintaining community connections. John McNiffe, Project Director for Balfour Beatty VINCI, highlighted the bridges’ role in delivering the HS2 project in Warwickshire and the increased connectivity it offers to the local community.
Bridge Completions in Warwickshire
Four major bridges have been completed in this part of Warwickshire in 2025. These include the Fosse Way and Offchurch Greenway bridges, the Welsh Road Underbridge, which opened in February, and the A46 box structure, which was completed in April. The HS2 project involves over 200 bridges, from foot and cycle bridges to large viaducts, such as the Colne Valley.
Conclusion
The Fosse Way and Offchurch Greenway bridges, constructed by Galldris for Balfour Beatty VINCI, are now open. These additions are part of the broader HS2 project in Warwickshire, which includes several other completed bridges and future developments.
Company Summary
Galldris: Delivered the Fosse Way and Offchurch Greenway bridges on behalf of Balfour Beatty VINCI for the HS2 project.
Balfour Beatty VINCI: The main works contractor for the HS2 project, responsible for the construction of the Fosse Way and Offchurch Greenway bridges.
HS2 Ltd: The organization overseeing the HS2 project, with Vicki Lee as Senior Project Manager.
“`