Koralm High-Speed Rail Project: Austria, Klagenfurt-Graz

Austria’s Koralm High-Speed Railway, a €11 billion project, drastically cuts travel time between Klagenfurt and Graz, showcasing impressive railway engineering.

Koralm High-Speed Rail Project: Austria, Klagenfurt-Graz
October 28, 2021 1:02 am




Koralm High-Speed Railway – Railway Technology

Koralm High-Speed Railway – Railway Technology

This article delves into the engineering marvel that is the Koralm High-Speed Railway (HSR) line in Austria. The project, a testament to modern railway construction and a significant investment in Austria’s infrastructure, aims to dramatically reduce travel time between Klagenfurt (Carinthia) and Graz (Styria), two major Austrian cities. This ambitious undertaking involved overcoming considerable geographical challenges, necessitating innovative engineering solutions and substantial financial commitment. The project’s scope extends far beyond simply constructing a faster rail link; it encompasses significant advancements in tunneling technology, sustainable construction practices, and the creation of numerous jobs throughout its lifecycle. We will examine the project’s multifaceted aspects, from its initial planning and design phases through to the complex construction process and its anticipated impact on Austrian transportation and the economy.

Project Overview and Design

The Koralm HSR line’s primary objective is to significantly shorten the travel time between Klagenfurt and Graz, reducing it from approximately three hours to under one hour. This dramatic improvement is achieved through the construction of a 130km double-track electrified line incorporating cutting-edge railway technology. A key feature of the project is the 32.9km Koralm Tunnel, the longest railway tunnel in Austria, a feat of engineering that demanded meticulous planning and execution. The tunnel, bored through the challenging Koralpe mountain range, incorporates two parallel, mono-directional single-track tunnels connected by cross-passages every 500 meters, as well as an 830m emergency station midway through. Extensive geological and hydrogeological surveys, including 130 exploration wells and a 10km exploratory tunnel system, were conducted to ensure safe and efficient tunnel construction.

Construction Methodology and Challenges

The construction of the Koralm line was divided into several phases, each presenting unique challenges. The tunnel itself was divided into three sections (KAT1, KAT2, and KAT3) utilizing different construction methods. KAT1, the eastern entrance, employed the New Austrian Tunneling Method (NATM) or Sequential Excavation Method (SEM). KAT2, the longest section, utilized two 9.9m diameter Double-shield Tunnel Boring Machines (TBMs) for the simultaneous excavation of two parallel tunnels. KAT3 involved widening an existing tunnel and building a new section. Other sections of the line presented their own hurdles, including the construction of numerous bridges, viaducts, and underpasses, such as the underpass beneath the A9 Pyhrn motorway. The project also involved the relocation of existing railway lines and the construction of new stations.

Economic and Social Impact

The Koralm HSR project is not merely an infrastructure development; it’s a significant economic engine. The construction phase generated over 100,000 jobs, while the operational phase is expected to sustain approximately 40,000. Beyond job creation, the improved rail connection will enhance regional connectivity, boost tourism, and facilitate trade between Carinthia and Styria. Reduced travel times will make commuting easier and more efficient, ultimately improving the quality of life for residents in the affected regions. The project also demonstrates a commitment to sustainable development through careful consideration of environmental impact and the adoption of innovative, resource-efficient construction methods.

Project Summary and Conclusion

The Koralm High-Speed Railway represents a substantial achievement in Austrian railway engineering and infrastructure development. The project successfully navigated numerous logistical and engineering challenges, culminating in a state-of-the-art high-speed rail line that drastically improves connectivity between two important Austrian regions. The project’s scale and complexity are reflected in the significant investment (€11 billion) and the numerous jobs created during both construction and operation. The Koralm Tunnel stands as a testament to advanced tunneling technology and meticulous planning. This project showcases Austria’s commitment to modernizing its transportation network and fostering economic growth through strategic infrastructure investment. The anticipated operational start in 2023 (or later due to delays that may arise) will mark a new era for regional transportation, significantly impacting the lives of commuters, businesses, and tourists alike. The success of the Koralm HSR project serves as a valuable model for future large-scale railway undertakings globally, underscoring the importance of thorough planning, technological innovation, and effective collaboration to ensure efficient and sustainable development.

Project ParameterValue
Line Length130 km
Project Budget€11 billion ($13.8 billion)
Project TypeHigh-Speed Railway
ConnectionKlagenfurt – Graz
Number of Stations12
Koralm Tunnel Length32.9 km
Maximum Train Speed250 km/h
Expected Daily Train ServicesUp to 256

Company Information:

  • Turkish Railways (TCDD): State-owned railway company of Turkey.
  • Royal BAM Group: International construction company.
  • Aker Solutions: Global provider of engineering and construction services.
  • CEMEX Austria: A subsidiary of CEMEX, a global building materials company.
  • Strabag SE: European-based construction company.
  • Porr AG: Construction company based in Austria.
  • iC Group: Germany-based company providing environmental monitoring services.