Livingston Ave Bridge: 2026 Construction Update & Route Map

Albany’s Livingston Avenue Railroad Bridge undergoes $634.8M replacement, improving Empire Corridor rail efficiency and safety. Completion is slated for March 2028.

Livingston Ave Bridge: 2026 Construction Update & Route Map
August 12, 2024 1:53 pm

Livingston Avenue Railroad Bridge Replacement: Project Profile

The Livingston Avenue Railroad Bridge Replacement Project is a critical infrastructure initiative to replace a functionally obsolete 19th-century swing bridge with a modern, high-clearance vertical lift structure. This project will resolve a major operational bottleneck on the Empire Corridor, enhancing rail capacity, speed, and reliability for both Amtrak passenger and CSX freight services across the Hudson River between Albany and Rensselaer, New York.

AttributeDetails
Project NameLivingston Avenue Railroad Bridge Replacement
LocationHudson River, Albany, NY, USA (Milepost QC 143.1, Hudson Line)
Structure TypeSeven-span, double-track vertical lift bridge
Max Design SpeedSignificant increase from previous 15 mph restriction
Bridge LengthApproximately 1,300 ft (396 m)
Estimated Cost$634.8 million
Status (Q4 2025)Under Construction
Key ContractorsSkanska (Primary), HNTB, Garg Consulting, Creighton Manning Engineering

Technical Specifications

The core of the project is the construction of a new seven-span vertical lift bridge positioned immediately south of the existing structure. The design features two ballasted deck railroad tracks engineered to support modern, heavier freight loads (286,000 pounds) and accommodate taller rail cars. A key design element is a 2-foot higher top-of-rail elevation, which facilitates a deeper and more robust floor system while maintaining required navigational clearances. For maritime traffic, the project dramatically improves navigability by widening the channel beneath the main span from 100 feet to 190 feet. The project scope includes the full integration of modern control systems, machinery rooms, advanced signaling, and electrical infrastructure. Construction is phased to maintain traffic on the existing bridge until the final lift span is installed, minimizing disruption to the vital Empire Corridor. Approach work is also integral, involving upgrades to adjacent rail bridges over Water and Centre Streets in Albany and modifications to the triangular track junction in Rensselaer to improve train maneuverability.

Key Takeaways

  • Bottleneck Resolution: The new bridge eliminates a single point of failure on the 463-mile Empire Corridor, a critical passenger and freight route, by replacing a speed-restricted, low-capacity structure.
  • Enhanced Freight and Passenger Capacity: The double-track, high-load-capacity design will increase rail service reliability, reduce delays (which can currently reach 2.5 hours), and support economic growth by enabling more efficient freight movement.
  • Multi-Modal Infrastructure Integration: Beyond its railway function, the project incorporates a shared-use path for pedestrians and cyclists, creating a new, safe connection across the Hudson River and enhancing regional non-motorized transport networks.

Frequently Asked Questions (FAQ)

When will the new Livingston Avenue Bridge open?

The Livingston Avenue Railroad Bridge Replacement is scheduled for completion in March 2028. The project commenced in May 2024 and is currently under construction.

Who is building the Livingston Avenue Bridge?

The primary construction contractor for the Livingston Avenue Bridge replacement is Skanska. The project is a joint venture led by the New York State Department of Transportation (NYSDOT) in partnership with the Federal Railroad Administration (FRA) and involves a consortium of engineering firms.