Abuja-Kaduna Rail: 2026 Construction Update
Nigeria’s Abuja-Kaduna rail line, a standard-gauge railway project, boosts the country’s railway sector modernization. High-speed passenger and freight services improve transport and the economy.

Project Profile: Abuja-Kaduna Standard-Gauge Railway
The Abuja-Kaduna Standard Gauge Railway is a 186-kilometer line connecting Nigeria’s federal capital, Abuja, to the major northern commercial hub of Kaduna. As the first completed segment of Nigeria’s national railway modernization program, it serves as a critical technical and operational benchmark for high-capacity passenger and freight transport on the country’s new 1,435 mm gauge network.
| Attribute | Details |
|---|---|
| Project Name | Abuja-Kaduna Standard Gauge Railway |
| Location | Nigeria |
| Route | Idu (Abuja) – Rigasa (Kaduna) |
| Length | 186 km |
| Track Gauge | 1,435 mm (Standard Gauge) |
| Design Speed | 150 km/h |
| Estimated Cost | USD $874 million |
| Status | Operational (Commissioned July 2016) |
| Key Contractor | China Civil Engineering Construction Corporation (CCECC) |
| Primary Financier | China EXIM Bank / Federal Government of Nigeria |
Technical Specifications
The project’s scope involved the construction of a 186 km single-track standard-gauge line with nine stations. The civil engineering works were extensive, including the construction of 30 railway bridges, five of which are box bridges. A key structural component was the use of precast T-beams, each weighing 120 tons and standing 2.5 meters high, reflecting the high-capacity design requirements. The line incorporates modern signaling and communication systems to ensure safe and efficient operations, representing a significant technological leap from the legacy narrow-gauge infrastructure it was designed to replace.
Rolling stock consists of modern Diesel Multiple Units (DMUs) for passenger services and diesel locomotives capable of hauling freight trains with a capacity of up to 800 tons. This dual-purpose design enables the line to serve both as a vital commuter link and a logistics corridor, enhancing economic integration between Nigeria’s administrative capital and its northern regions.
Key Takeaways
- Modernization Blueprint: The project’s successful execution established the technical and financial model for subsequent standard-gauge projects in Nigeria, including the Lagos-Ibadan and Itakpe-Warri lines, validating the national strategy of transitioning from narrow gauge.
- Economic Corridor Catalyst: By providing a safe, reliable, and faster alternative to road transport, the railway has created a vital economic corridor. It has significantly reduced travel times, improved connectivity, and stimulated commercial activity between Abuja and Kaduna.
- Strategic Infrastructure Development: The line demonstrates a viable model for large-scale infrastructure financing in the region, blending national funding with concessional loans from international partners like China’s EXIM Bank, and has spurred local capacity building in railway construction and operations.
Frequently Asked Questions (FAQ)
When did the Abuja-Kaduna train service start?
The Abuja-Kaduna train service officially commenced commercial operations in July 2016, making it the first operational standard-gauge railway in Nigeria.
Who built the Abuja-Kaduna railway?
The Abuja-Kaduna railway was constructed by the China Civil Engineering Construction Corporation (CCECC), with financing provided through a strategic partnership between the Nigerian Federal Government and the Export-Import Bank of China.